Learn project management test questions MCQs, advance project management test for learning online courses and test prep to practice. Management of conflicts and negotiation quiz has multiple choice questions (MCQ), project management test questions quiz questions and answers, requirements and principles of negotiation, partnering, chartering and scope change, project management test questions tutorials for online application for project work courses distance learning.

Advance project management practice test MCQ: causes for change in projects are basically of with choices 2 types, 3 types, 4 types and 6 types problem solving skills for summative and formative assessment, competitive exam prep, interview questions with answer key. Free study guide is for online learning project management test questions quiz with MCQs to practice test questions with answers.

MCQs on Project Management Test Questions Quiz PDF Download

MCQ. Causes for change in projects are basically of

  1. 2 types
  2. 3 types
  3. 4 types
  4. 6 types

B

MCQ. An increase in user or team knowledge or sophistication is primary factor leading to

  1. Scope
  2. Scope change
  3. Strategy
  4. Innovation

B

MCQ. Problem of changing scope or performance, expected of a project is a major

  1. Drawback
  2. Issue
  3. Downfall
  4. Success

B

MCQ. Despite of how carefully a project is planned, it is almost certain to be changed before

  1. Execution
  2. Planning
  3. Completion
  4. Assigning resources

C

MCQ. Cause of change that cannot be managed by PM is

  1. Technological Uncertainty
  2. Innovation
  3. Change in environment
  4. Increased client knowledge

C