Negotiation and Conflict Management Multiple Choice Questions 1 PDF Download

Learn negotiation and conflict management multiple choice questions (MCQs), advance project management test 1 for online learning, course exam prep. Practice conflicts and project life cycle MCQs, negotiation and conflict management questions and answers on conflicts and project life cycle test for online cloud based project management softwares courses distance learning.

Free negotiation and conflict management quiz online, self-study student guide has multiple choice question: three of fundamental issues are delimiting technical objectives, setting projects relative priority and with choices management commitment, establishing project councils, establishment of unions and contractual procedures for online viva voce, competitive exams' preparation and online distance educational learning. Study to learn online conflicts and project life cycle quiz questions with advance project management MCQs for Project Management Professional (PMP) certification competitive exam prep.

MCQ on Negotiation and Conflict Management Test 1

MCQ: Three of fundamental issues are delimiting technical objectives, setting project?s relative priority and

  1. Establishing Project Councils
  2. Management commitment
  3. Establishment of unions
  4. Contractual procedures

B

MCQ: If project is organized as a weak matrix, PM seeks a commitment of work from the

  1. Personnels
  2. Subcontractors
  3. Senior Management
  4. Functional Department

D

MCQ: Third task to be achieved at Project formation phase is

  1. Defining Scope
  2. Budgeting
  3. Resource Allocation
  4. Prioritizing the project

D

MCQ: Specifying technical objectives to a degree, allows

  1. Detailed Budgeting
  2. Detailed planning
  3. Detailed cost estimates
  4. Detail resource allocation

B

MCQ: Groups that band together to do what is necessary to complete project on time and to specification, is

  1. PM and Functional groups
  2. Functional Groups
  3. PM , project team and Functional group
  4. PM and Project team

C