Learn customer response time and on time performance MCQs, cost accounting test for online learning courses, test prep to practice test. Balanced scorecard: quality, time and theory of constraints quiz has multiple choice questions (MCQ), customer response time and on time performance quiz questions and answers, quality: competitive tool, financial perspective: costs of quality, bottlenecks, customer response time and on time performance tutorials for online bachelors degree courses distance learning.

Cost accounting practice test MCQ: if value added manufacturing time is 65 minutes, total manufacturing time is 80 minutes, then manufacturing cycle time will be with choices 0.8125, 0.6125, 0.9125 and 1.725 for online tutoring, subjective theory tests and online associate of business degree preparation. Free study guide is for online learning customer response time and on time performance quiz with MCQs to practice test questions with answers. Customer Response Time and On Time Performance Video

MCQs on Customer Response Time and On Time Performance Quiz PDF Download

MCQ: If value added manufacturing time is 65 minutes, total manufacturing time is 80 minutes, then manufacturing cycle time will be

  1. 0.8125
  2. 0.6125
  3. 0.9125
  4. 1.725

A

MCQ: Sum of manufacturing and waiting time for an order is classified as

  1. manufacturing efficiency time
  2. manufacturing cycle time
  3. responding time
  4. value chain time

B

MCQ: Consumed time to deliver a complete order to its customers is termed as

  1. responding time
  2. value chain time
  3. delivery time
  4. manufacturing cycle efficiency

C

MCQ: Time between a customer's order placement till customer receives its delivery is known as

  1. manufacturing lead time
  2. manufacturing cycle time
  3. customer response time
  4. system process time

C

MCQ: Timeframe between placement of order until a finished good produces is classified as

  1. customer response time
  2. manufacturing lead time
  3. manufacturing cycle time
  4. both b and c

D