Strategic Management and Projects Selection Multiple Choice Questions and Answers 1 PDF eBooks Download

Learn strategic management and projects selection multiple choice questions (MCQs), advance project management test 1 online for exams. Practice project portfolio process MCQs questions and answers on project portfolio process with answers. Free strategic management and projects selection quiz, online study guide has helping answer key with choices as collect data, identify project criteria, assess resource and establishment of council of multiple choice questions (MCQ) as first step in project portfolio process (ppp) is to test learning skills for viva exam preparation and job's interview questions. Study to learn project portfolio process quiz questions to practice online MCQs for competitive exam preparation test.

MCQ on Strategic Management and Projects Selection Test 1

MCQ. First step in Project Portfolio Process (PPP) is

  1. Identify Project Criteria
  2. Collect Data
  3. Assess Resource
  4. Establishment of Council

D

MCQ. A schedule of project activities, past experience, expert opinion, whatever is available to get a good estimate of the

  1. Time
  2. Data
  3. Strategy
  4. Vision

B

MCQ. Sixth step in Project Portfolio Process is

  1. Collect Project Data
  2. Assess Resource Availability
  3. Reduce Criteria Set
  4. Prioritize Projects within Categories

D

MCQ. "Interesting" projects may not contribute to the

  1. Validation
  2. Strategy
  3. Reliability
  4. Subjective

B

MCQ. Subjective evaluations can be translated from verbal to numeric terms easily through

  1. Account Method
  2. Framing Method
  3. Delphi Method
  4. Assembly Method

C